NPK Nitrate Based 100.000 MTPY — Project Control Dashboard
Cikampek, Karawang – Jawa Barat | Kontrak: Rp 558,9 M | ED: 12 Nov 2025 | Mech. Completion: Jun 2027
WEEKLY REPORT W-22 31 Mar – 6 Apr 2026
OVERVIEW
📋 ANALISA
S-CURVE
ENGINEERING
PROCUREMENT
CONSTRUCTION
HSE & QC
RISK & ISSUE
Overall Progress
13.90%
Plan 14.29%AHEAD
SPI
0.973
Variance +0.07%
Engineering
48.19%
Plan 51.94%DELAY −3.74%
Procurement
55.17%
Plan 58.64%DELAY −3.46%
Construction
35.68%
Plan 32.34%AHEAD +3.34%
Distribusi Bobot (Weight Factor)
Kontribusi setiap disiplin terhadap overall progress
Progress Aktual vs Plan per Disiplin
Perbandingan kumulatif W-22
⚙️
Engineering
WF 10% · DELAY −3.74%
Kumulatif 48.19% vs plan 51.94%. Delay −3.74%.
Piping (10.27% vs 7.68%) & 3-D (17.01% vs 14.66%) ahead.
Civil delay −1.11%. Jalur kritis: Spec Sheet UPS & Battery Charger (EEL007/008/009/011) @ 40%, target selesai 5 Mei 2026.
📦
Procurement
WF 55% · DELAY −0.35%
Kumulatif 55.17% vs plan 58.64%. DELAY −3.46%.
Total 42 requisisi: 15 PO selesai, 27 ongoing, 9 delayed.
Delayed: MV System, Electrical Cable Tray FRP.
Near-critical: Dosing Package (float 4.4 hari).
🏗️
Construction
WF 30% · AHEAD +3.34%
Kumulatif 35.68% vs plan 32.34%. AHEAD +3.34%.
Piling Elec.Room 55/60, CCR 16/16 (done), Process Plant 73/262 titik.
Civil Work 1.73% vs plan 0.63% (AHEAD). Concern: Drawing Substation menunggu Engineering.
S-Curve Physical Progress
Plan vs Actual vs Forecast (Kumulatif)
Plan
Actual
Forecast
Plan Inc.
Actual Inc.
Summary Progress per Disiplin
Kumulatif W-22 · 13 April 2026
Disiplin
WF
Plan
Actual
Plan/Actual
Dev
Status
Project Item Concerns W-22
Isu aktif yang perlu tindak lanjut
🔴 Pemasangan CCTV di Area Proyek OPEN
Surat No. 00809/C/PP/D2600/PK/2026. Target: 6 Apr 2026. Rekind segera melakukan pemasangan CCTV. PIC: Construction Manager.
🟡 Geopolitical Tensions — Dampak Middle East ke Proyek INFO
Rekind menginformasikan potensi dampak global akibat kondisi geopolitik Timur Tengah terhadap supply chain material dan equipment. PIC: Project Manager.
✅ Proyeksi DrawDown Triwulan NPK Nitrat CLOSED
Surat No. NPKNPKC-PM-LTR-000-0041. Rekind telah mengirim proyeksi drawdown triwulan. Closed 31 Maret 2026.
27 Aktivitas Kritis | Total Float = 0 Hari | Scheduled Completion: 19 Juli 2027
Sedang BerjalanBelum Mulai (Kritis)MilestoneData Date (14 Apr 2026)● Eng● Proc● Cons● Comm
Sumber: NPK_PKC_INT_260414.xer | Critical Path Type: Total Float ≤ 0 | Data Date: 14 April 2026
Analisis Critical Path — NPK Nitrate Based 100.000 MTPY
Critical Tasks
28
Float = 0 hari
Near Critical
10
Float 1–5 hari
Mech. Completion
20 Mei 2027
Main Process
Scheduled Finish
19 Jul 2027
Plant Acceptance
🔴 Bottleneck Utama (Saat Ini)
● UPS & Battery Charger System adalah jalur kritis tunggal penentu jadwal proyek
● 6 dok. Engineering (Spec Sheet & SLD) sedang berjalan 40% — target selesai 5 Mei 2026
● RFQ progress 50% — harus selesai 114 Apr 2026
● Keterlambatan apapun akan langsung menggeser tanggal Mech. Completion
📋 Urutan Jalur Kritis
① Engineering Spec & RFQ → Apr–Mei 2026
② TBE & PO UPS System → Apr–Mei 2026
③ Fabrikasi & Delivery UPS → Mei 2026–Jan 2027
④ Instalasi & Power Energized → Jan–Feb 2027
⑤ Motor Solo Run + Running Test → Feb–Mei 2027
⑥ Mechanical Completion → 20 Mei 2027
⚠ Risiko & Rekomendasi Project Control
Risiko Tinggi:
● 6 aktivitas Engineering aktif serentak — risiko resource conflict
● Gap 7+ bulan antara PO (Mei 2026) dan Instalasi (Jan 2027) — risiko delivery delay
● Power Energized (Feb 2027) adalah single-point-of-failure commissioning
Rekomendasi:
● Monitor mingguan Spec Sheet & RFQ — prioritas tertinggi bulan ini
● Percepat TBE & negosiasi PO agar fabrikasi dimulai lebih awal
● Siapkan contingency plan jika delivery UPS terlambat >2 minggu
Analisis berdasarkan Primavera P6 XER — NPK_PKC_INT_260414 | Data Date: 14 April 2026 | Total Aktivitas: 1.985
📊
Belum ada data
Upload file XLSX, PPTX, dan XER melalui tombol di header untuk melihat analisis otomatis.
Distribusi Top Risk per Kategori
Menunggu data PPTX…
Status Requisisi Procurement
Menunggu data PPTX…
Tren Deviasi Payment Fisik (Kumulatif)
Plan vs Actual per week — dari sheet S-CURVE
Plan W-22
14.29%
Actual W-22
13.90%
Forecast W-23
16.23%
SPI
0.973
S-Curve Overall — Physical Progress Kumulatif
W1 (18 Nov 2025) → W89 (26 Jul 2027)
Plan Kumulatif
Actual Kumulatif
Forecast
S-Curve + Progress Incremental per Minggu
Kumulatif (garis) vs Progress Mingguan/Incremental (batang) — W1 s/d W22
Plan Kumulatif
Actual Kumulatif
Forecast Kumulatif
Plan Incremental
Actual Incremental
S-Curve Physical + Milestone
Payment basis kumulatif
Plan
Actual
Forecast
Plan Inc.
Actual Inc.
Tren Deviasi Progress per Minggu
Actual − Plan (%) kumulatif W-14 s/d W-22 (Overall Progress)
Komposisi Progress W-22 per Disiplin
Kontribusi aktual setiap disiplin ke overall (×WF)
Tabel Payment Milestone W-14 → W-22
Kumulatif Plan vs Actual
Week
Plan Cum
Actual Cum
Deviasi
W-14
9.20%
9.89%
+0.69%
W-15
11.56%
12.03%
+0.47%
W-16
12.20%
12.73%
+0.53%
W-17
12.75%
13.26%
+0.51%
W-18
13.42%
14.42%
+1.00%
W-19
13.75%
14.78%
+1.03%
W-20
14.82%
15.21%
+0.39%
W-21
15.62%
15.67%
+0.05%
W-22
16.87%
16.51%
-0.36%
Cum. Actual
48.19%
Cum. Plan
51.94%
Deviasi
−3.74%
Forecast W-23
44.64%
Progress per Sub-Disiplin Engineering
Plan vs Actual kumulatif W-22
Distribusi Aktual Engineering
Proporsi kontribusi aktual per sub-disiplin
Rencana Issuance W-22 (Next Week)
Target 7–13 April 2026 · Total: 14 dok IFA + 11 dok IFC
Disiplin
Plan Progress
Target Progress
IFA
IFC
Status
Project Management
0.13%
0.00%
0
0
—
Process
0.86%
0.00%
0
0
—
Process Safety
0.00%
0.07%
1
0
TARGET
Mechanical
0.45%
0.08%
2
0
OK
Piping
0.04%
0.00%
0
0
—
Electrical
0.57%
0.27%
2
11
OK
Instrument
0.19%
0.00%
1
0
TARGET
Civil
0.90%
0.32%
9
0
OK
3D Model
0.65%
0.00%
0
0
—
TOTAL
3.13%
0.74%
14
11
Engineering Concerns W-22
Hambatan jalur kritis
🔴 Delay Approval P&ID Main Process OPEN
Masalah: P&ID dari Licensor (ESPINDESA) baru diterima akhir Feb 2026, perlu Re-IFA. Tindak Lanjut: Konsinyering Pra-HAZOP. Target Re-Issue W1 April 2026. PIC: Lead Process Engineer.
🟠 Delay MDS Dosing Package OPEN
Masalah: MDS menunggu PDS dari Process sebagai input. Impact: Delay proses RFQ dan PO. Tindak Lanjut: Expedite PDS Dosing Package.
🟡 Layout Main Process Building — Revisi Plot Plan CONTINUE
Masalah: Plot Plan dari Licensor berubah, revisi multi-disiplin diperlukan. Tindak Lanjut: 3D model update ongoing. Release layout piling area yang tidak terdampak. Target: W1 April.
42
Total Requisisi
15
PO Selesai
27
Ongoing
5
Delayed
Status Requisisi Procurement
Distribusi 42 requisisi per status
Progress Procurement per Kategori
Plan vs Actual kumulatif W-22
Distribusi Bobot Procurement
Weight factor per kategori material
Awarded Vendors & Subkontraktor
15 paket telah diaward per W-22
#
Paket
Vendor
Delivery
1
Temp. Facilities
PT Kelda Prima Mandiri
22 Mei 26
2
Site Preparation
PT Hurip Utama
23 Mar 26
3
Soil Investigation
PT Soilens
31 Mar 26
4
PC Spun Pile
PT Wika Beton
25 Apr 26
5
Steel Structure P-2
PT Bangun Sarana Baja
30 Sep 26
6
Install Steel P-2
PT Bangun Sarana Baja
31 Des 26
7
Piling Work
PT Pakubumi Semesta
2 Jun 26
8
Steel Structure P-1 (PEB)
PEB Steel Buildings
31 Des 26
9
Import Soil
PT Reka Solusi Arthamedia
13 Apr 26
10
Civil & Arch. Pkg-1
PT Sarana Abadi Raya
3 Feb 27
11
Rotary Drum P-1
PT Global Niaga Internusa
23 Agu 26 FOB
12
Rotary Drum P-2
PT Global Niaga Internusa
23 Agu 26 FOB
13
Pipe CS Seamless Batch-1
PT Paradise Perkasa
8 Jun 26
14
CS Fittings Flanges
PT Artifisial Teknologi Persada
17 Apr 26
15
Bagging System
Premier Tech Systems
14 Nov 26 FOB
Near-Critical Items Procurement
Item berisiko terhadap jadwal proyek
🔴 PLC System — Estimasi PO: End April 2026 NEAR CRITICAL
TBE/CBE dalam proses. Target PO terbit akhir April 2026. Potensi delay jika RFQ dan evaluasi tidak selesai tepat waktu.
🟠 UPS & Battery Charger — RFQ Proses NEAR CRITICAL
Dalam proses RFQ. Target delivery DDP Site 13 Apr 2026.
🟡 Bagging System (Premier Tech) — KOM Done ON TRACK
KOM 31 Mar 2026 selesai. VPC form-1 / vendor print schedule disubmit 6 April. FOB Thailand 14 Nov 2026.
🟡 Rotary Drum (GNI) — VPC Under Review ON TRACK
KOM 4 Maret 2026. VPC form-1 return 30 Mar 2026. FOB Shanghai 23 Agustus 2026.
Cum. Actual
35.68%
Cum. Plan
32.34%
Deviasi
+0.87%
Total Piling Terpasang
448
dari est. 1.071 tiang
Status Piling per Area
Update 13 April 2026
Distribusi Piling — Done vs Sisa
Total tiang terpasang vs rencana per area
Construction Activity Status W-22
Realisasi vs Target
Aktivitas
Lokasi
Realisasi
Target
Status
Piling
Bagging & Palletizing
69 / 69 nos
30 Mar 26
DONE ✓
Piling
Electrical Room
49 / 60 nos
8 Apr 26
ON TRACK
Piling
Main Process Bldg
65 / 166 nos
Apr 26
PENDING DRWG
Piling
Product Warehouse
248 / 248 nos
Mar 26
DONE ✓
Furniture Temp. Office
Temp. Facilities
48 / 52 set
4 Apr 26
ON TRACK
Mushola Atap
Temp. Facilities
88 / 88 m²
4 Apr 26
DONE ✓
Excavation Foundation
Product Warehouse
In Progress
—
ONGOING
HSE Performance — W-21 | 7 Apr – 13 Apr 2026
PROYEK NPK NITRATE BASED 100.000 MTPY — PT REKIND EPC
Total Jam Kerja Selamat (Man-Hours Without LTI)
118.787
jam kerja | Kumulatif sejak 12 Nov 2025 s.d. 13 Apr 2026 | 0 LTI
Fatality
0
kejadian
LTI
0
kejadian
LTIFR
0.00
per juta jam
Nearmiss
0
akumulatif W-22
First Aid
2
kasus
Property Damage
0
kejadian
📈 Tren Jam Kerja Selamat per Minggu
Man-hours kumulatif W-1 s.d. W-22 tanpa LTI
🔴 Lagging Indicators — Rekap Insiden
Kategori kejadian sejak awal proyek (W-1 s.d. W-22)